October 2018: Programming scheduled to begin after October 30 ribbon cutting.

August 2018: Park and community center restroom construction is underway.

February 2018: Work scheduled to begin after groundbreaking February 20.

December 2017: City Council approved bond funding for project.  

June 2017: Conceptual park rendering supported by East Side Neighborhood.  Construction documents are being prepared.

April 2017: Second park rendering developed based on East Side Neighborhood feedback.

March 7, 2017: Draft rendering shared with East Side Neighborhood Association for feedback.

February 2017: Draft park rendering developed.

February 2017: City Council approved an additional $250,000 for project.

November 2015: City Council approved using $318,000 from Section 108 Loan toward project.